Friday, April 27, 2007

Day Eight

About 8:00p.m.. The rafters are all up and you
can really get a feel for what the cabin will look
like. I even added one of the twelve light
windows so you can see what it looks like in place.
After much head scratching, I started to put up the rafters
late this afternoon. There are other roofs that would have
been easier to build, but I love a gable roof- the steeper, the
better. This is a 12:12 roof, (45 degrees),but if I didn't have to do all the work
by myself, I would have gone even steeper.



Here's one of the rafters I made today. This one didn't
make the cut. Making rafters is hard. These are a sort
of hybrid between traditional rafters and a truss system.
Rafters are lighter, but must be put up two at a time- tough
for one set of hands. A truss is too heavy and uses the space
above the ceiling (no loft). These are assembled on the gound,
(the loft actually- the only flat, open area left) and then raised
one set at a time. They are then married to the the loft joists
as a reinforcement.

The windows are here! Eight windows and french doors.

How do you make a tiny space seem roomier and more

open? Glass was my answer. We'll see how it turns out.



Today was one of those days when I couldn't really get going. I haven't seen another person
in a week and today I had three different visitors. One was the Building Inspector who was "just wondering what was going on."

Thursday, April 26, 2007

Day Seven

I managed to move all the lumber inside and then I made a template
of the rafters so I could measure the seat cuts where they will sit on
the walls.
This is what the loft looks like from downstairs.

Here I am on top of the sleeping loft. I still have to
nail down the floor/ ceiling boards. First I have to see how
the rafters will sit.

Rick in his new house.




After the reverie of completing four walls, I decided to get back to work.
These ceiling joists will support the sleeping loft and reinforce the walls
as the roof presses out.


Maybe I should have invested in a tool box.



Number Four!
Here's the south wall, framed and up, but not sheathed so
I can access the inside easily.

And it's up! Ultimately nothing but brute force was going to
raise this wall and unfortunately I was the brute. There
were a couple of dicey moments when I wasn't sure what was going to happen and I can't honestly say how much this wall weighs because I think there may
have been some sort of spiritual intercession.
Here's another. The come-a-long simply pulled the wall straight
out instead of lifting it up.

I decided to side the east wall before raising it. That might

not have been the best idea. Wet lumber, wet siding, load bearing wall-

so a double top plate, windows four feet wide-so double headers there, sill plates,

cripple studs, trimmer studs, and king studs. Basically it weighed a ton.

This is one of the methods of raising the east wall that didn't work.


P:M: Momentous day. Rick and I got to the property early and the weather held all day.


A.M.: Up at 4:00 so we can use whatever good weather there is. Forecast for the next few days is not promising so I hope to get the walls up and figure out a way to cover the cabin well enough to keep the rain out. More later.

Wednesday, April 25, 2007

Day Six

P.M.: Irony really only works in literature and film, in real life it just sucks. The rain finally let up at around 8:00 pm tonight, just as it was getting too dark to work anymore. I managed to frame the east wall which means all four are done, but I would like to have had them all raised and sided by tonight. The good news is that the east wall is a knockout, three big windows, (not in- just framed). That wall will be almost completely glass. Rick and I are going to try to get up very early tomorrow morning so we can take advantage if the weather's good. Hopefully some more encouraging pictures tomorrow.
This tarp did a so-so job of keeping the rain out.


A.M.: You can battle time and you can battle the weather and you know what? You'll lose twice. The sprinkles have ended and the showers have taken their place. I'm in a tough spot right now where there's very little I can do in a full blown storm. Ricky refuses to stay under the tarp so I have returned to the motel and will go back to the site alone with the hope for a brief break in the weather so I can work on the other two walls, affix the tarp, and have a place to work should it rain again.

Tuesday, April 24, 2007

Day Five


This is the scene as I leave at eight p.m.. The inside of the

two completed walls and the frame for the south wall on the subfloor.

I would like to have raised this wall too, but I ran out of time. My goal

is to have all four walls up tomorrow so I can put up some sort of

temporary roof before the rains come.


The west wall is up! In a somewhat harrowing experience,
I sided the wall before raising it. A little scary and very heavy. The siding
is over the window openings. I'll open them up when
time allows.

This is the frame for the west wall. Note the framing

for the two windows. Both windows are twelve light antiques

I found at a building salvage yard. The third matching

window will be located on the south facing wall beside a

set of french doors.

All the siding is on and the wall is up!


P.M.: Some rain today, but then it cleared up and Rick and I got a lot of work done. We saw a deer on the property this morning and heard several turkeys. Ricky did his duty and kept the worksite clear of all wild things.


A.M.: Misting and cooler this morning. The forecast calls for seven straight days of rain starting on Day Seven. Sounds Biblical. My only hope is that it will hold off long enough for me to put up the three other walls and affix a temporary roof. I'll frame the windows but I'll sheathe over them to keep the inside dry, leaving the installation for better weather. Rick and I are up early and on our way. Hopefully we'll have some pictures tonight.

Monday, April 23, 2007

Day Four

Now the wall has been sheathed in builder's felt and partially
sided. Unfortunately, it started raining and Rick and I were
forced to leave the rest for tomorrow.
Once I braced the plumb wall, I removed the cables and
used them to make sure the wall was square. Placed at
the exact same height and length along the floor, the
cable length should be exactly the same.


These short chains make sure that as I push the wall up,

I don't push it right over the edge.


These cable braces have two functions: they keep me from

pushing the wall too far and once the wall is braced, the turnbuckles
help to plumb the wall.
You may not be able to tell, but this wall
is actually braced in five places.


And the wall is up!



Here is the north wall, framed up and laid out on the floor.

No windows in this wall since prevailing winter winds come from

that direction.



Rookie carpenter's hands. Note the blister on my ring

finger. Ricky, lacking opposable thumbs left most of the

hammering to me.



Here we are on the newly finished subfloor. Ricky tracked
mud all over it.




I would like to have been a little further along, but I am not all that disappointed. Finishing up the subfloor took considerably longer than I had expected and what followed proved to be the most exciting project yet. Raising walls is absolutely nerve-racking and exhilirating. Finally three dimensions. Several pictures follow, many of which show some tools and techniques I developed, (or at least I think I did), for dealing with this difficult task alone. They worked surprisingly well.

Sunday, April 22, 2007

Day Three

Here are the joists with the vapor barrier in place
This picture shows all the joists in place as well as the
tarp I put up after my sunburn became too much to
bear

The new generator

My Workbench: 2x4s stacked on a wheelbarrow
because somebody (probably Ricky) forgot that you need
two sets of sawhorse brackets

Tough day today. Things took longer than I had hoped. I decided today that you could probably accomplish three times as much with only one more set of hands. The right tools would help too. See the above picture of my makeshift work station. I also ended up drilling quite a few pilot holes to assist construction, (note that I had no drill bits and the hardware store was closed, so I broke off half a galvanized 16 penny nail and used it for the drill bit. It worked pretty well. I got most of the subfloor down today and will include a picture tomorrow when it is done.
Sidenote: Tongue and groove subfloor installed by yourself, not a good idea.

Saturday, April 21, 2007

Day Two

The finished foundation: pressure treated beams over a
bed of crushed stone. Level and even, a little tougher
than you might think. Add moving all that lumber to the
site by hand, and I had a long day. Water consumed: 1.5
gallons.
So tired. These picture do not relate the 10-12 hours of
wild turkey chasing that preceded them.


I built a small retaining wall of fieldstone.


tired puppy




Still a lot to do.